041200P.pdf 01/18/2005 Cameo Homes v. Kraus-Anderson
U.S. Court of Appeals Case No: 04-1200
District of Minnesota
Civil case - contracts. District court did not err in finding plaintiff had
failed to satisfy the contractual condition precedent to litigation because it
had not given written notice of its breach of contract claims to the project
architect; failure to provide the written notice also precluded plaintiff's
assertions of negligence against the City of East Grand Forks; project
manager acted within the scope of the contracts and incurred no
additional obligation to plaintiff when it required verification of
plaintiff's work; there was no evidence project manager played any role
in furnishing plans or had any duty to verify blueprints, and plaintiff
could not state a negligence claim for providing inaccurate plans.
[PUBLISHED] [Murphy, Author, with Hansen and Melloy, Circuit Judges]