051441P.pdf 08/08/2005 Emerson Electric Co. v. Guy Rogers
U.S. Court of Appeals Case No: 05-1441
Eastern District of Missouri
[PUBLISHED] [Murphy, Author, with Riley and Smith, Circuit
Judges]
Civil case - Contracts. District court did not err in granting plaintiff's
motion for a preliminary injunction because plaintiff was likely to
succeed on its claim that defendant had violated his covenant not to
compete, plaintiff had shown the likelihood of irreparable harm and the
equities favored defendant.