141892P.pdf 05/26/2015 Unison Co., Ltd. v. Juhl Energy Development, Inc.
U.S. Court of Appeals Case No: 14-1892
U.S. District Court for the District of Minnesota - Minneapolis
[PUBLISHED] [Kelly, Author, with Gruender and Shepherd, Circuit Judges]
Civil case - Arbitration. The relevant language of the supply contract
between the parties covered any dispute that arose in connection with the
agreement or any legal relationship associated with or contemplated by the
supply agreement and was broad enough to cover a dispute arising out of
the parties' separate financing agreement; the district court erred,
therefore, in denying a motion to compel arbitration; on remand, the
district court should determine whether it is appropriate to dismiss the
action or stay the action. Judge Shepherd, concurring.